Principal Investigator:Van Stempvoort, Dale R. Licensed Year(s):
2005
Summary:
The objectives of this study are to 1) address information gaps with respect to groundwater quality and quantity along the proposed pipeline corridor; 2)gather groundwater information along the corridor between Fort Simpson and Great Bear Lake; 3) examine remediation processes for, and results of, petroleum spills in the north; and 4) help the Department of Transportation investigate potential gro...
Principal Investigator:Johnson, Pascale Licensed Year(s):2006
2005
200420032002 Summary:
The Pointed Mountain Gas Plant, six associated wellsites, and the airstrip are being assessed during the decommissioning process. The site was initially constructed in 1966. The plant has been shut down since September 2001. The Pointed Mountain field has had soil, groundwater, and surface water assessed since 1990. Previous environmental work and public consultation at this site have identifi...
Principal Investigator:Graburn, Larry Licensed Year(s):
2004
2003 Summary:
The objective of this program is to carry out aerial reconnaissance and preliminary site investigations, topographical aerial mapping, and surface reconnaissance in the general vicinity of the proposed route for the Mackenzie Gas Project. Information fro...
Principal Investigator:Miller, Samantha Licensed Year(s):
2003
2002 Summary:
The objectives of this assessment are to conduct a soil investigation and remediation associated with the flare stack at the Paramount Resources Ltd. F-36 Wellsite. In August 2002, a modified Phase II Environmental Site Assessment was conducted. The bas...
Principal Investigator:Povey, Andrew Licensed Year(s):2004
2003
2002 Summary:
These terrestrial studies will include vegetation and soils investigations. The primary goals are to classify vegetation, landforms, soils and permafrost in the project area, to identify locations of rare plants and uncommon plant communities, and to co...