Principal Investigator:Hamm, Sharleen Licensed Year(s):
2006
Summary:
In view of Peregrine Diamonds Ltd.’s move to advance the DO-27 kimberlite pipe of the WO Diamond Project to the pre-feasibility assessment phase, this project is proposed to collect baseline data that would contribute to an Environmental Assessment in subsequent years. Gartner Lee Ltd has been contracted to undertake field sampling, which will consist of examining surface water quality; hydrology;...
Principal Investigator:Moore, Peter Licensed Year(s):2004
2003
Summary:
Dillon Consulting Limited has been retained to complete habitat restoration activities at the historic Salmita Mine site at Matthews Lake. The 2003 phase of this project is to conduct baseline aquatic assessments at the Matthews Lake site to identify pr...
Principal Investigator:Sekerak, Aaron D. Licensed Year(s):
1990
Summary:
The Researcher and his assistant will obtain information on fish in the area so that potential impacts of mining in the region can be assessed....