3 record(s) found in the location "Dehcho Region" (multi-year projects are grouped):
Not seeing the results you want? Tryadvanced search.

Phase III ESA - Fort Simpson RCMP Detachment
Principal Investigator: Schulz, Eva
Licensed Year(s): 2013
Summary: The main objective of the Phase III Environmental Site Assessment is to delineate the hydrocarbon contamination at the site resulting from an overflow of fuel at a vent pipe of an above ground storage tank. Test holes will be excavated with a backhoe around the former spill area in order to collect soil samples. Each sample will be submitted to a Canadian Association for Laboratory Accreditatio...


Phase II Environmental Site Assessment at Pointed Mountain Gas Plant and Associated Facilities
Principal Investigator: Stone, Larry
Licensed Year(s): 2006 2005 2004 2003 2002
Summary: The Pointed Mountain Gas Plant, four associated wellsites, and some associated infrastructure are being decommissioned. The site was originally constructed in 1966 and has been shut down since September 2001. Previous environmental work and public consul...


Modified Phase II-III Environmental Site Assessment F-36 Wellsite
Principal Investigator: Miller, Samantha
Licensed Year(s): 2003 2002
Summary: The objectives of this assessment are to conduct a soil investigation and remediation associated with the flare stack at the Paramount Resources Ltd. F-36 Wellsite. In August 2002, a modified Phase II Environmental Site Assessment was conducted. The bas...