Principal Investigator:DeMontigny, Dallas Licensed Year(s):
2018
Summary:
The objectives of the survey is to identify potential sensitivities in the area and help develop avoidance or mitigation measures. This will be done through a ground reconnaissance survey. The surveys include preliminary archaeological, wildlife, vegetation, and fish habitat.
The surveys will be conducted by foot patrol and shovel test pits if required. Local people will assist in the surveys. ...
Principal Investigator:Kors-Olthof, Rita I Licensed Year(s):
2014
2011 Summary:
The overall goal is to describe the environmental conditions present along the trail and bridge site for planning purposes to avoid, minimize, and/or mitigate potential impacts to the natural, resource, and cultural features along the proposed road and bridge alignment. The priority for observations will be between the turn-off from Bickish Avenue to about 800 m west of the proposed bridge locatio...
Principal Investigator:Seligman, Ben Licensed Year(s):
2007
2006 Summary:
The proposed fieldwork is an expansion of previous years' fieldwork to develop a suitable knowledge base for planning and development. In addition, some routine maintenance at Camp Farewell will be conducted. The majority of the proposed work is planned for the Niglintgak area and is focused around the Gas Conditioning Facility (GCF) and the Horizontal Directional Drilling (HDD) crossing site, as ...
Principal Investigator:Martin, Sandy D Licensed Year(s):
2006
Summary:
The proposed biophysical and reconnaissance studies are aimed at collecting data to assess the feasibility of constructing a potential oil and gas pipeline for the Mackenzie Gas Project. The 2006 work programme includes: route and site reconnaissance; aquatic and terrestrial studies; and engineering, geological and geophysical studies.
Route and site reconnaissance comprise: verification of the ...
Principal Investigator:Martin, Sandy D Licensed Year(s):
2006
Summary:
The proposed biophysical and reconnaissance studies are aimed at collecting data to assess the feasibility of constructing a potential oil and gas pipeline for the Mackenzie Gas Project. The 2006 work programme includes: route and site reconnaissance; aquatic and terrestrial studies; and engineering, geological and geophysical studies.
Route and site reconnaissance comprise: verification of the ...
Principal Investigator:Martin, Sandy D Licensed Year(s):
2006
Summary:
The proposed biophysical and reconnaissance studies are aimed at collecting data to assess the feasibility of constructing a potential oil and gas pipeline for the Mackenzie Gas Project. The 2006 work programme includes: route and site reconnaissance; aquatic and terrestrial studies; and engineering, geological and geophysical studies.
Route and site reconnaissance comprise: verification of the ...
Principal Investigator:Martin, Sandy D Licensed Year(s):
2006
Summary:
The proposed biophysical and reconnaissance studies are aimed at collecting data to assess the feasibility of constructing a potential oil and gas pipeline for the Mackenzie Gas Project. The 2006 work programme includes: route and site reconnaissance; aquatic and terrestrial studies; and engineering, geological and geophysical studies.
Route and site reconnaissance comprise: verification of the ...
Principal Investigator:Povey, Andrew Licensed Year(s):
2005
200420032002 Summary:
The objective of this study is to complete several helicopter flights for the purposes of pipeline and site reconnaissance and geotechnical observation. The activities will be conducted to: review the proposed location for a potential gas pipeline through the Sahtu Settlement Area (SSA), including identifying areas where mitigation measures may be required during or after construction such as stee...
Principal Investigator:Povey, Andrew Licensed Year(s):
2005
200420032002 Summary:
The route and site reconnaissance activities will be used to: review the proposed location for a potential gas gathering system and potential pipeline route through the Inuvialuit Settlement Region; revisit or determine the optimal locations for infrastructure sites, roads, granular resource sites, water withdrawal sites, and potential revegetation test sites; visually inspect and confirm land for...
Principal Investigator:Povey, Andrew Licensed Year(s):
2004
20032002 Summary:
Imperial Oil Resources Ventures Limited, Aboriginal Pipeline Group, ConocoPhillips Canada (North) Limited, Shell Canada Limited, and ExxonMobil Canada Properties are continuing baseline studies begun in 2001 as part of the Mackenzie Gas Project. This por...